Sections

Weather Forecast

Close
Advertisement

Baxter updates Wildflower, Franklin and Woida project timeline

Email Sign up for Breaking News Alerts
news Brainerd, 56401
Brainerd MN 506 James St. / PO Box 974 56401

BAXTER — An assessment hearing for the Wildflower, Franklin and Woida road

project in Baxter is planned May 20.

Construction is expected to begin in the first part of July.

Advertisement
Advertisement

Tuesday the Baxter City Council approved plans and specifications for the project along with advertising for bids. A bid opening is expected April 29 during a special council meeting. The assessment appeal periods ends June 19. According to the project timeline, another special council meeting is scheduled June 24 for the notice of the construction award with work to begin July 9. The project should be complete by Oct. 24.

The council has been meeting regularly in closed sessions to make property and easement acquisitions.

Advertisement
Brainerd Dispatch customer support
I've worked at the Brainerd Dispatch with various duties since Dec. 7, 1983. Starting off as an Ad Designer and currently Director of Audience Development. The Dispatch has been an interesting and challenging place to work. I'm fortunate to have made many friends, both co-workers and customers.
(218) 855-5889
Advertisement
Advertisement